Free tool

Earned Value Management (EVM) Calculator

Enter planned value, earned value, actual cost and budget to see whether your project is on schedule and on budget, and where it is heading.

SPI0.9EV ÷ PV

Behind schedule: only 90% of the planned work is done.

CPI0.94EV ÷ AC

Over budget: each 1 spent earns only 0.94 of value.

Schedule variance (SV)-5,000EV − PV

Value of work behind plan.

Cost variance (CV)-3,000EV − AC

Spent more than the value earned so far.

Estimate at completion (EAC)1,28,000BAC ÷ CPI

Forecast total cost if current cost efficiency continues (budget 1,20,000).

Estimate to complete (ETC)80,000EAC − AC

Forecast spend still needed to finish the project.

Variance at completion (VAC)-8,000BAC − EAC

Forecast to finish over budget.

TCPI1.04(BAC − EV) ÷ (BAC − AC)

Cost efficiency needed on remaining work to land on the original budget.

What is earned value management?

Earned value management (EVM) is a way of measuring project performance that combines scope, schedule and cost into one picture. Instead of asking only “how much have we spent?” or “are we on the timeline?”, EVM asks how much of the planned value has actually been delivered for the money spent. That single question exposes problems that budget reports and Gantt charts hide on their own, such as a project that is on budget only because work is running late.

The four inputs

  • Planned value (PV): the budgeted cost of the work that should be complete by now according to the schedule.
  • Earned value (EV): the budgeted cost of the work that actually is complete. If 40% of a 100,000 budget is done, EV is 40,000.
  • Actual cost (AC): what has really been spent to get the work done so far.
  • Budget at completion (BAC): the total approved budget for the whole project.

The most common mistake is confusing EV with AC. Earned value is measured in budget terms (what the completed work was supposed to cost), while actual cost is what it did cost.

EVM formulas

SPI = EV ÷ PVSchedule Performance Index: work done versus work planned.
CPI = EV ÷ ACCost Performance Index: value earned per unit of money spent.
SV = EV − PVSchedule Variance, in currency. Negative means behind.
CV = EV − ACCost Variance, in currency. Negative means over budget.
EAC = BAC ÷ CPIEstimate at Completion: forecast total cost.
ETC = EAC − ACEstimate to Complete: forecast spend still to come.
VAC = BAC − EACVariance at Completion: forecast overrun or saving.
TCPI = (BAC − EV) ÷ (BAC − AC)Efficiency needed on remaining work to hit budget.

A worked example

A project has a total budget (BAC) of 120,000. By the end of month three the plan said 50,000 of work should be done (PV), but only 45,000 of work is actually complete (EV), and the team has spent 48,000 (AC).

  • SPI = 45,000 ÷ 50,000 = 0.90: the project has delivered 90% of the work it planned, so it is behind schedule.
  • CPI = 45,000 ÷ 48,000 = 0.94: every 1 spent produces 0.94 of value, so it is slightly over budget.
  • SV = 45,000 − 50,000 = −5,000 and CV = 45,000 − 48,000 = −3,000.
  • EAC = 120,000 ÷ 0.94 ≈ 128,000, so at the current efficiency the project will overrun by roughly 8,000.
  • ETC = 128,000 − 48,000 ≈ 80,000 still to spend.

These are the default values in the calculator above, so you can change one input at a time and see how each metric responds.

How to read the results

Look at SPI and CPI together. A project that is behind schedule but under budget (SPI < 1, CPI > 1) is often simply under-resourced: the team is spending less because fewer people are working on it. A project that is ahead of schedule but over budget may be buying speed with overtime or contractors. The worst quadrant is both indices below 1.0, which usually points to scope or estimation problems that need a conversation with the sponsor, not just a recovery plan.

Trends matter more than a single reading. A CPI that has fallen from 1.05 to 0.94 over three months says more than a CPI of 0.94 on its own, which is why tracking these numbers continuously beats calculating them once for a steering committee.

EVM on agile projects

Agile teams can use the same formulas by measuring value in story points. Planned value comes from the points the release plan expected to finish by now, and earned value from the points actually completed to your Definition of Done. Your sprint velocity gives the expected pace, and cost per point turns points into money for CPI.

Tracking EVM continuously

A calculator is useful for a quick check, but spreadsheets go stale. Taskmei records planned value, earned value and actual cost per project and shows SPI and CPI on the project delivery and executive dashboards alongside RAG status and open risks, so leaders see the trend without waiting for a monthly report.

What is a good SPI or CPI?

An index of 1.0 means exactly on plan. Above 1.0 is better than plan (ahead of schedule for SPI, under budget for CPI); below 1.0 is worse. Many organisations treat 0.9 to 1.1 as acceptable and investigate anything outside that band.

What is the difference between EAC and ETC?

Estimate at Completion (EAC) is the forecast total cost of the whole project. Estimate to Complete (ETC) is only the remaining spend from today, so ETC equals EAC minus the actual cost so far.

Which EAC formula does this calculator use?

It uses EAC = BAC ÷ CPI, which assumes the current cost efficiency continues for the rest of the project. Other formulas exist, such as AC + (BAC − EV) when past overruns are not expected to repeat, or ones that combine CPI and SPI. Choose the one that matches your situation.

Can I use EVM on agile projects?

Yes. Agile EVM measures earned value from completed story points against the planned points for a release, which lets you report SPI and CPI to sponsors without abandoning sprints. The key is defining 'earned' as work that meets your Definition of Done.

What does TCPI tell me?

The To-Complete Performance Index is the cost efficiency you must achieve on the remaining work to finish on the original budget. A TCPI well above 1.0 means the budget is unlikely to hold without changing scope or funding.

Track SPI and CPI on every project

Taskmei shows earned value, RAG health and top risks on live dashboards. Free plan available.