Sprint Planning Template
Plan a sprint on one page: the sprint goal, the team's capacity and the backlog items the team commits to.
Template preview
- Sprint
- Sprint 14
- Sprint goal
- Customers can reset their password without contacting support
- Dates
- 13 Oct – 24 Oct 2026 (10 working days)
- Team capacity
- 155 focused hours / about 29 story points
- Committed
- 29 story points
| ID | Backlog item | Type | Story points | Priority | Owner | Acceptance criteria (summary) | Status |
|---|---|---|---|---|---|---|---|
| TM-142 | Request a password reset link by email | Story | 5 | High | Asha | Link sent within 2 min; same message for unknown emails | To Do |
| TM-143 | Set a new password from the reset link | Story | 5 | High | Ravi | Link single-use, expires after 24 h; password rules enforced | To Do |
| TM-144 | Email confirmation after password change | Story | 3 | Medium | Meera | Confirmation sent; includes 'not you?' support link | To Do |
| TM-151 | Login fails on Safari 17 | Bug | 3 | High | Ravi | Login works on Safari 17 desktop and iOS | To Do |
| TM-152 | Evaluate rate limiting for reset requests | Spike | 2 | Medium | Asha | Recommendation documented with chosen approach | To Do |
| TM-153 | Automated tests for reset flow | Task | 8 | Medium | QA | End-to-end tests cover happy path and expiry | To Do |
| TM-154 | Update help-centre article | Task | 3 | Low | Meera | Article reviewed and published | To Do |
Example rows shown. The download includes extra blank rows ready for your team.
How to use this template
- Agree the sprint goal. Start with one sentence describing the outcome of the sprint. Every committed item should contribute to it.
- Calculate capacity. Subtract leave and holidays, apply a focus factor and convert hours to points using recent velocity.
- Pull items from the top of the backlog. Take refined, estimated items in priority order until the total approaches capacity.
- Confirm acceptance criteria. Make sure every item has clear, testable criteria the team understands.
- Commit and share. Record the committed total, share the plan with stakeholders and start the sprint.
Tips
- Commit to 80–90% of capacity to leave room for surprises.
- If an item is bigger than a few days of work, split it before planning.
- Review carry-over from the last sprint before adding new work.
Run it as a live board instead
Spreadsheets go out of date the moment the sprint starts. In Taskmei the same information lives on a live board: backlog items, sprints, risks and Definition of Done stay current and feed dashboards automatically. Use this template in Taskmei on the free plan.
Related resources
Sprint Capacity Calculator for Scrum Teams
Plan realistic sprints: calculate team capacity in hours from availability, time off and focus factor, then convert it to story points.
OpenSprint Velocity Calculator and Sprint Forecast
Calculate your Scrum team's average sprint velocity from past sprints and forecast how many sprints your remaining backlog needs.
OpenUser Story Template with Acceptance Criteria
Free user story template in the As a / I want / So that format with acceptance criteria and story points.
OpenFrom template to live board in minutes
Free Taskmei workspace with Scrum, Kanban and Hybrid boards. No credit card required.